How to Develop a Subdivision Step by Step

How to Develop a Subdivision Step by Step

Learn how to develop a subdivision from raw land to finished lots. Covers entitlements, budgeting, timelines, financing, and construction management.

Updated February 12, 2026

Recently Funded
Cash-Out Refinance

$5.3M Industrial Warehouse

Birmingham, AL

Developing a subdivision is one of the most profitable paths in real estate, but it is also one of the most complex. From finding the right parcel of land to recording a final plat, the process spans multiple phases that can take 18 to 36 months or longer. Understanding each step before you begin helps you avoid costly surprises and keeps the project moving on schedule.

This guide walks you through how to develop a subdivision from start to finish. Whether you are planning a 10-lot infill project or a 200-lot master-planned community, these steps apply. We will cover land evaluation, entitlements, budgeting, timelines, financing, construction management, and common mistakes that derail first-time developers.

If you are actively planning a subdivision project and need financing for land acquisition, horizontal construction, or vertical building, contact Clearhouse Lending for a free consultation. Our advisors specialize in structuring loans across every phase of development.

Need Financing for This Project?

Stop searching bank by bank. Get matched with 6,000+ vetted lenders competing for your deal.

What Are the Steps to Developing a Subdivision?

Subdivision development follows a predictable sequence of phases that begins with market research and ends with lot sales or vertical construction. Most projects move through nine core steps, though the exact order and duration depend on the municipality, site conditions, and project scope.

The core steps include market research and feasibility analysis, land acquisition, due diligence, preliminary plat submission, engineering and design, entitlement approvals, site grading and infrastructure installation, final plat recording, and lot sales or vertical construction. Each phase has its own deliverables, cost drivers, and approval gates.

According to The Land Development Site, the entire process "can take at least a few weeks to a few months" for simple subdivisions, but larger developments with rezoning requirements or environmental constraints routinely span two to three years.

How Do You Find and Evaluate Land for Subdivision Development?

Finding the right parcel is the single most important decision you will make. A site that looks affordable on paper can become a money pit if the zoning is wrong, the soil cannot support septic systems, or the access roads are inadequate. Thorough evaluation before you sign a purchase agreement protects your entire investment.

Start by defining your target market. Are you building entry-level single-family homes, luxury estate lots, or townhome communities? Your product type determines the minimum lot size, density requirements, and price points you need. Once you know the product, work backward to identify parcels that meet your criteria.

Key evaluation factors include:

  • Zoning and land use designation - Verify the parcel is zoned for residential use at the density you need. If rezoning is required, add 6 to 12 months and significant risk to the timeline.
  • Topography and soil conditions - Flat or gently sloping land with good drainage costs far less to develop than hilly terrain or sites with high water tables. Order a geotechnical study early.
  • Utility access - Proximity to public water, sewer, electric, and gas lines matters. Extending utilities a half mile can add $500,000 or more to your budget.
  • Road access and traffic - The site needs frontage on a public road or an approved access easement. Traffic studies may be required for developments above a certain lot count.
  • Environmental constraints - Wetlands, floodplains, endangered species habitats, and contaminated soil can limit buildable area or require expensive mitigation.

For a deeper look at evaluating and purchasing development land, read our Land Acquisition Financing Guide.

What Entitlements and Approvals Are Required?

Entitlements are the legal permissions you need from local government before you can develop raw land into a subdivision. Without them, you cannot record a plat, pull permits, or begin construction. The entitlement process is often the longest and least predictable phase of development.

Most jurisdictions follow a two-step approval process: preliminary plat and final plat. Some also require a concept plan review before the preliminary submission. Depending on your project, you may also need rezoning, conditional use permits, variance approvals, environmental impact assessments, traffic impact studies, and stormwater management plans.

The preliminary plat shows the proposed lot layout, road network, utility routing, drainage plans, and open space designations. It goes through a review by the planning commission and typically requires a public hearing. According to MRSC, preliminary plat review is "a quasi-judicial process that involves an initial review and public hearing by the city or county planning commission."

After the preliminary plat is approved (often with conditions), your engineering team prepares detailed construction drawings. The final plat incorporates any modifications required during preliminary review and must demonstrate compliance with all conditions of approval. Final plat approval is generally a ministerial process, meaning if you meet the stated conditions, approval must be granted.

For a comprehensive overview of the entitlement process, see our Real Estate Entitlements and Zoning Guide.

How Do You Create a Subdivision Development Budget?

A subdivision development budget must account for every dollar spent from land acquisition through lot delivery. Underestimating costs is one of the primary reasons new developers run into financial trouble. Building a detailed budget with appropriate contingencies keeps your project solvent.

Typical subdivision development costs break down into four major categories: land acquisition (20% to 35% of total budget), hard costs for infrastructure (35% to 45%), soft costs for design, engineering, and fees (15% to 25%), and contingency reserves (5% to 15%). These percentages vary by market and project complexity.

According to Angi, site development costs in 2025-2026 average roughly $30,000 per lot for infrastructure alone, though this figure can range from $15,000 to $75,000 per lot depending on site conditions, utility requirements, and local standards. Street improvements typically run $200 to $260 per front foot of lot, including side street allowances.

Here is what to include in each budget category:

Land Acquisition Costs:

  • Purchase price
  • Closing costs and title insurance
  • Due diligence expenses (surveys, environmental studies, geotechnical reports)
  • Carry costs during entitlement (property taxes, insurance, loan interest)

Hard Costs (Infrastructure):

  • Mass grading and earthwork
  • Road construction (subgrade, base, curb, gutter, asphalt or concrete)
  • Water distribution system
  • Sanitary sewer system
  • Storm drainage and retention/detention facilities
  • Electric, gas, and telecom conduit
  • Landscaping and common area improvements

Soft Costs:

  • Civil engineering and land planning
  • Surveying
  • Architectural design (if building homes)
  • Legal and accounting fees
  • Permit and impact fees
  • Marketing and sales costs
  • Project management and overhead

Use our commercial mortgage calculator to estimate your debt service during the development period.

What Is the Timeline for Developing a Subdivision?

The timeline for developing a subdivision depends on the project's size, the local approval process, site conditions, and market conditions. A straightforward 20-lot subdivision with existing zoning might take 12 to 18 months. A 100-lot project requiring rezoning and major infrastructure can take 24 to 36 months or more.

Understanding the typical duration of each phase helps you plan cash flow, set investor expectations, and coordinate with contractors and buyers.

Phase-by-phase timeline breakdown:

  • Market research and feasibility (1-3 months): Evaluate the site, analyze comparable subdivisions, build a pro forma, and secure purchase option or contract.
  • Due diligence (2-4 months): Complete surveys, environmental studies, geotechnical analysis, and title research. This phase often overlaps with the feasibility period in your purchase contract.
  • Preliminary plat and entitlements (3-12 months): Submit plans, attend public hearings, respond to review comments, and negotiate conditions of approval. Rezoning adds 3-6 months.
  • Final engineering and final plat (2-4 months): Prepare construction drawings, finalize utility agreements, and obtain final plat approval from the governing body.
  • Infrastructure construction (4-12 months): Grade the site, install roads and utilities, build stormwater facilities, and complete landscaping. This is where your horizontal construction loan draws down.
  • Final inspections and lot delivery (1-2 months): Pass all municipal inspections, record the final plat, and deliver finished lots to builders or begin vertical construction.

For more detail on pre-development planning, read our Pre-Development Financing Guide.

How Do You Secure Financing for Each Phase of Development?

Subdivision development requires different types of financing at different stages. Most developers cannot self-fund a multimillion-dollar project, so structuring the right capital stack is critical. The financing strategy you choose affects your returns, your risk exposure, and your ability to move quickly through each phase.

The typical financing structure for a subdivision moves through three stages: land acquisition financing, a land development or horizontal construction loan, and optionally a vertical construction loan if you are building the homes yourself rather than selling finished lots to builders.

Land Acquisition Financing: This initial loan covers the purchase of the raw land. Expect lenders to require 25% to 40% down payment on raw land. Loan terms are typically 12 to 24 months. Interest rates run 7% to 10% for most borrowers. Many developers negotiate a longer feasibility period in their purchase contract so they can complete due diligence before the loan closes.

Horizontal Construction (A&D) Loans: Acquisition and development loans fund both the land purchase and infrastructure installation. These loans typically cover 50% to 65% of total project costs and draw down in stages as construction milestones are met. Terms run 18 to 36 months with interest rates of 7% to 11%. Clearhouse Lending structures horizontal construction loans for subdivision developers nationwide.

Vertical Construction Loans: If you plan to build homes on the finished lots, you will need a separate construction loan for each phase of home building. These loans fund materials, labor, and subcontractor costs. Terms are usually 12 to 18 months per phase, with draws tied to completion of foundations, framing, and finishing milestones. Learn more about structuring these loans in our guide to Horizontal vs Vertical Construction Loans.

Bridge Financing: Bridge loans fill gaps between phases, such as carrying finished lots while you wait for builder takedowns. These short-term loans (6-12 months) provide liquidity when you need it most.

Need financing for your subdivision project? Contact Clearhouse Lending for a custom loan structure. We can pre-qualify your project in 24 hours.

What Are the Most Common Mistakes New Subdivision Developers Make?

Even experienced real estate investors stumble when they enter subdivision development for the first time. The combination of municipal approvals, engineering complexity, and long timelines creates many opportunities for costly errors. Knowing these pitfalls in advance gives you a significant advantage.

According to DevRes, insufficient financial planning is the most damaging mistake, as "developers often underestimate costs or overestimate potential returns, leading to budget overruns, delays, and financial strain." Here are the most common mistakes and how to avoid them.

1. Skipping thorough due diligence. Many developers assume a parcel is buildable based on surface-level information. Failing to investigate title exceptions, utility easements, environmental constraints, and soil conditions can lead to discovering that a critical portion of the site is undevelopable after you have already closed on the land.

2. Underestimating the entitlement timeline. First-time developers often assume approvals will take three months when the actual process takes nine months or longer. Budget for the worst case and use option contracts to limit your financial exposure during the entitlement period.

3. Ignoring neighborhood opposition. Community resistance at public hearings can delay or kill a project. Engage early with adjacent property owners and neighborhood groups. Consider hosting an informational meeting before the formal hearing process begins.

4. Underbudgeting infrastructure costs. Infrastructure costs frequently exceed initial estimates by 15% to 30%. Rock removal, unexpected utility relocations, and upgraded stormwater requirements are common culprits. Always carry a 10% to 15% contingency on your hard costs budget.

5. Choosing the wrong financing structure. Using short-term financing for a long-timeline project creates unnecessary pressure. Match your loan terms to realistic project timelines, and build in extension options where possible.

6. Failing to understand the local market. Building 50 luxury lots in a market that absorbs 10 per year creates a carrying cost nightmare. Match your project scale and product type to actual demand, validated by comparable sales data.

How Do You Manage the Construction Phase of Subdivision Development?

The construction phase is where your plans become reality and where cost overruns most frequently occur. Effective project management during horizontal construction keeps the project on budget and on schedule. This phase typically represents 35% to 45% of your total development budget.

Managing subdivision construction requires coordinating multiple contractors, meeting municipal inspection requirements, and controlling draw schedules tied to your horizontal construction loan. Here is how to manage it effectively.

Hire an experienced site contractor. Your general contractor or site work contractor should have specific subdivision development experience, not just home building or commercial construction experience. Ask for references from completed subdivision projects and verify their bonding capacity covers your project scope.

Establish a clear draw schedule. Work with your lender to establish construction milestones tied to loan draws. Common draw milestones include mass grading completion, road subgrade installation, utility rough-in, curb and gutter, final paving, and final landscaping. Each draw is typically verified by a third-party inspector.

Monitor progress against the critical path. Subdivision construction has a logical sequence. You cannot pave roads until utilities are installed in the road bed. You cannot install curbs until the road subgrade is compacted. Identify the critical path items and monitor them weekly. Delays in early phases compound throughout the project.

Keep detailed records. Document all change orders, weather delays, inspection reports, and contractor communications. These records protect you in disputes and help you provide accurate reporting to your lender and investors.

Use our commercial bridge loan calculator to model your carry costs during the construction phase.

What Should You Know About Platted Subdivisions and Lot Sales?

Once construction is substantially complete and the municipality accepts the infrastructure, you can record the final plat and begin selling finished lots. The transition from developer to seller introduces a new set of considerations around pricing, marketing, and builder relationships.

A platted subdivision is a legally recorded division of land into individual lots with defined boundaries, easements, and rights-of-way. Recording the plat allows individual lots to be conveyed to builders or homebuyers.

Lot pricing strategies:

  • Comparable sales approach - Price your lots based on recent finished lot sales in comparable subdivisions within a five-mile radius.
  • Residual land value approach - Work backward from finished home prices to determine what builders can afford to pay for lots (typically 20% to 25% of the finished home price).
  • Phased release - Release lots in phases to maintain scarcity and increase prices as the subdivision gains momentum.

Builder takedown agreements are contracts where builders commit to purchasing a set number of lots on a predetermined schedule. These agreements provide predictable cash flow and help you project loan payoff dates. Most lenders look favorably on projects with signed takedown agreements.

For more information about financing the full subdivision lifecycle, read our guide on How to Finance Subdivision Development.

What Do Developers Ask Most About Subdivision Projects?

How much does it cost to develop a subdivision?

Infrastructure costs alone typically range from $15,000 to $75,000 per lot, with $30,000 per lot as a common national benchmark. A 50-lot subdivision with moderate infrastructure needs might have a total budget of $3 million to $6 million including land. Impact fees can add $5,000 to $30,000 per lot depending on the jurisdiction.

How long does it take to develop a subdivision from start to finish?

Most subdivisions take 18 to 36 months from land acquisition to finished lot delivery. Small infill projects with existing zoning can finish in 12 to 18 months. Large projects requiring rezoning or phased infrastructure can take three to five years.

Do I need to be a licensed contractor to develop a subdivision?

In most states, you do not need a contractor's license to develop a subdivision as long as you hire licensed contractors for the construction work. You may need a real estate license to sell finished lots in some states. Check your state's licensing requirements before starting.

What is the difference between a subdivision and a land development?

A subdivision is the legal process of dividing a larger parcel into smaller lots. Land development is the physical process of improving those lots with roads, utilities, and drainage. Most projects involve both. Our guide on horizontal construction loans covers the financing side of land development.

Can I develop a subdivision on land that is not zoned residential?

Yes, but you will need to apply for a rezoning, which adds time, cost, and uncertainty. Rezoning requires public hearings and governing body approval, which is never guaranteed. Experienced developers either target land already zoned for their use or negotiate purchase contracts contingent on rezoning approval. See our Real Estate Entitlements and Zoning Guide for a full breakdown.

What return on investment should I expect from subdivision development?

Developer profit margins typically range from 15% to 30% of total development costs, depending on market conditions and execution. Builder-developers who also construct homes generally earn higher returns because they capture margin at both the lot and home sale stages.

TOPICS

subdivision development
land development process
real estate development
subdivision steps
developer guide

Clear House Lending Team

Commercial Lending Experts

Our team of commercial lending experts brings decades of experience helping investors and developers secure the right financing for their projects.

Ready to Explore Your Options?

Connect with our team for a free consultation and personalized financing quote from our network of 6,000+ commercial lenders.

Get a Free Quote

Related Articles

View all

Commercial Loan Programs

Financing solutions for every stage of the commercial property lifecycle

Commercial financing

Ready to secure your next deal?

Fast approvals, competitive terms, and expert guidance for investors and businesses.

  • Nationwide coverage
  • Bridge, SBA, DSCR & more
  • Vertical & Horizontal Construction Financing
  • Hard Money & Private Money Solutions
  • Up to $50M+
  • Foreign nationals eligible
Chat with us